PROJECT CASESTUDY
On-time, on-budget and no snags after ‘go live’

DHL Aberdeen
- Project Size: 12,000 Sq ft
- Location: Aberdeen
- Activity: Commercial Fitout & Refurbishment
- Duration: 8 weeks

CLIENT BRIEF
With the planned demolition of DHL’s base at Aberdeen Airport – they required a new depot within the airport complex to move into. They had a non-negotiable eviction date and the new building needed a lot of work complete before they moved in.




Having worked with DHL on a number of previous refurbishments throughout the UK, Calibro had the knowledge and skill to complete the project on time and to the budget.


DHL’s new base provides 12,000 ft2 of warehousing/parcel transfer space with a link corridor to the new Portacabin semi-permanent offices.



This was the only project this year to be completed on-time, on budget and didn’t have any snags after we went ‘live’.
DHL Aberdeen
OTHER PROJECTS
Ulster Carpets
Office design for leading carpet manufacturer in London
Forsa Santry
Meeting and breakout design for office space in Dublin
Kerr Henderson
Design & Build office refurbishment for financial services client.
Download
Thank you, your resource has opened in a new tab. If you do not see your resource please allow pop-ups or click the View Resource button above.